How does an ADU permit work in Los Angeles County?

Ike Mbelu, Principal Partner · Last checked

On this page: The short answer · What the code says · Where you file

The short answer

What the code says

  1. 01

    Complete or not in 15 business days

    The agency must tell you in writing whether the application is complete within 15 business days. Miss that, and it is deemed complete. Gov. Code 66317(a)(2).

  2. 02

    Sixty days to decide

    The 60 days run from a completed application on a lot with an existing home. An ADU filed with a new house can wait for the house decision, and a delay you ask for tolls the clock. Gov. Code 66317(a)(3).

  3. 03

    A denial lists what to fix

    A denial comes with written comments listing each deficiency and how to cure it. Only an ADU ordinance consistent with state law can be the basis for delay or denial. Gov. Code 66317(b), (c).

  4. 04

    You can appeal

    An incomplete or denied application has a written appeal, decided within 60 business days of the appeal. Gov. Code 66317(d). These rules took this form January 1, 2026 (SB 543).

Where you file

  1. 01

    Unincorporated LA County

    County Title 22 applies only to unincorporated land. There the unit must also meet requirements set by Public Works Building and Safety and the Fire Department. LACC 22.02.030.A.1. See ADU rules in LA County.

  2. 02

    Inside a city

    The city is the permitting agency. Same state clock, its own ADU code: Gardena · Torrance · Hawthorne · Carson · Bellflower · Lawndale · Redondo Beach. Garage plans: garage conversion.

This is a summary of the California Government Code and the Los Angeles County Code, not legal advice. Confirm the current code for your site.